Structural Steelwork Projects in the Health Sector
Previous successful projects for our key clients has resulted in their request for our expertise for structural steelwork projects within the health sector.
The tight lead times and programme durations for this type of contract are complemented by the just-in-time production processes at our workshop in Carnwath. This just-in-time philosophy ensures that all BHC sites are fed in a timeous fashion, ensuring minimal handling on-site and achievement of programmes.
Current and recent health sector steelwork projects include:
Southern General Hospital Neo Natal
Location:
Glasgow (commencing July 2008)
Client: Balfour Beatty
Steelwork: 260 tonnes
Hospital Construction Project
Location:
Lochgilphead - Argyll
Client: Balfour Beatty
Steelwork: 450 tonnes
Royal Infirmary, Multi-storey Parking Facility
Location:
Glasgow
Client: Laing O'Rourke
Steelwork: 880 tonnes; Concrete: 4,000 precast panels
10 week programme - completed in 8 weeks